Incoming Inspection: How to Verify a Supplier's Certificates

Published:

Summary of the article

Incoming inspection verifies a supplier's certificates against the purchase order, the marking on the tool and a source the supplier doesn't control before the tool is accepted. The checks run in order: document set, certificate type, licence marking, heat number, physical measurement. A mismatch means the tool is held and a non-conformance report is raised.

Incoming inspection verifies a supplier's certificates by checking each document against the purchase order, against the marking on the tool and against a source the supplier does not control, before the tool is accepted. The checks run in a fixed order: document set, certificate type, licence marking, heat number, then physical measurement. When the paper and the tool disagree, the tool is held and a non-conformance report is raised.

Incoming inspection, also called receiving inspection or goods receipt inspection, is a control point between a supplier's dispatch and a tool's release for use. The sequence below covers certificate verification at goods receipt for a completion tool. It is written for the QA engineer who runs the check and the completion supervisor who accepts the tool at the wellsite. It shows which documents should arrive, how to check each one against the tool rather than against itself, how to verify a licence mark on the API Composite List, what each EN 10204 certificate type changes, and what to do when something does not match. Here is the short version.

What does a certificate check at goods receipt involve, in brief

A certificate check at goods receipt has seven steps, and each step compares a document with something outside the supplier's own paper: the purchase order, the marking on the tool, a public register or a measurement.

  • The purchase order sets what must arrive and which EN 10204 type each material certificate must be.
  • The certificate type decides who validated it: type 3.1 by the manufacturer's authorised inspection representative, independent of production, and type 3.2 with a second validator added.
  • Where the order calls for a monogrammed tool, the mark and licence number on the tool are searched on the API Composite List at receipt, because statuses change.
  • The heat number on the certificate must match the marking on the component, and the original mill certificate is requested when results were transferred.
  • Dimensional and visual checks are done with your own instruments, not read from the supplier's report.
  • A mismatch means the tool is held and a non-conformance report is raised, and the decision to reject, hold or accept with a concession is recorded with the name of who made it.

What is incoming inspection actually for

Incoming inspection is the check a buyer runs when purchased goods arrive, to confirm that what arrived is what was ordered and that the documents describe it, before it is released for use. It has two halves:

  • Document review reads the certificates and records against the purchase order.
  • Physical verification checks the tool itself against the drawing, the marking and the documents.

Document review shows that the documents agree with each other. It does not show that they are true. Physical verification, and checks against sources the supplier does not control, supply the missing proof.

ISO 9001 clause 8.4 covers the control of externally provided products and services, so a purchased product such as a completion tool falls under it. ISO 9001 clause 8.6 sets the release rule: a product is released only after the planned verification arrangements are completed, unless a relevant authority, and where applicable the customer, approves otherwise. The release record traces to the person who authorised it.

Teams also call this receiving inspection or goods receipt inspection, and many record the result on a goods receipt note (GRN). The scope is one shipment at receipt. It is not the supplier audit and it is not the factory test, and a later part of this guide draws that line. Before any check can run, the receiving team needs to know which documents should be on the table.

Which documents should arrive with a completion tool, and what must each one show

The documents that arrive with a completion tool are set by the purchase order, so the first job at goods receipt is to read the order's documentation clause and tick off what arrived. The table below lists what each document must show and what it is matched to.

DocumentWhat it must showWhat it is matched to
Material test report (MTR) or certificateHeat or lot number, grade and specification, chemistry and mechanical results, the EN 10204 type, and the signatory or inspection body.The order's material and certificate-type requirement, and the marking on the component.
Certificate of conformanceThe part number and revision, the order reference, a statement of compliance with the order, and a named signatory.The purchase order line and the drawing revision.
Dimensional inspection reportThe features measured, nominal values and tolerances, actual values, and the instrument or gauge identification.The drawing, and your own spot measurements.
Pressure test certificate (or function test certificate)The tool serial number, test pressure, test medium, hold time, result, and the witness or inspector.The order's test requirement and the serial number marked on the tool.
Marking and licence evidence, where the order calls for the API MonogramThe mark and licence number on the tool or nameplate, and the same number on the conformance document.The API Composite List, checked as the licence step later in this guide describes.
Traceability record (or marking record)The link from the tool's serial or lot number to the heat number.The markings on the component and the material test certificate.
Packing listQuantities, part numbers, serial numbers and the order reference.What is on the pallet, and the purchase order.

How to read each field of a material test report is its own subject and is not covered here.

Row 5 exists because of a marking rule. Only an API licensee may apply the API Monogram and its designated licence number, and both are applied in the marking sequence at the location the product specification identifies.

Management-system certificates for quality, environment and safety are not per-shipment documents. They belong in the supplier-qualification file, and they are checked on the accreditation database when the supplier is approved and again at each file review. With the document set on the bench, the order of checks comes next.

How do you verify the certificates, step by step

A certificate check at goods receipt runs in seven steps, and every step names the source the document is checked against. The order puts the cheapest and most decisive checks first.

  1. Read the order. Find the documents and the certificate types it requires. Checked against: the purchase order.
  2. Count the set. Every document the order requires is present, and each one names the same part number, revision, order reference and serial or lot number. Checked against: the order and the drawing.
  3. Check the type. Each material certificate carries the EN 10204 type the order asked for. Checked against: the order.
  4. Check the validator. See who signed. For a type 3.2, the second body is named as well. Checked against: the certificate and the order.
  5. Check the licence marking where the order requires it, on the public register, as the next section describes. Checked against: the register.
  6. Match the heat number and grade to the component, as the section after that describes. Checked against: the marking on the tool.
  7. Measure and inspect, then decide. Checked against: your own instruments.

The EN 10204 type tells you who stands behind the test results:

EN 10204 typeValidated byWhat to check at receipt
Type 2.1, declaration of complianceThe manufacturer.It contains no test results, so it cannot satisfy an order that requires results.
Type 2.2, test reportThe manufacturer.Results come from non-specific inspection and are not tied to your batch.
Type 3.1, inspection certificateThe manufacturer's authorised inspection representative, independent of the manufacturing department.The representative is named, and the heat number is tied to your material.
Type 3.2, inspection certificateThat representative, plus the purchaser's authorised inspection representative or an inspector designated by official regulations.The second validator is named and was arranged in advance.

A certificate marked EN 10204 3.1 must name its authorised inspection representative. A certificate issued by a test house that is neither a manufacturer nor an independent third party cannot be a type 3.2. A type 3.1 certificate must not be relabelled as a type 3.2 after delivery, and a type 3.2 needs its second validation planned with the supplier before the test, not after.

EN 10204 lets a manufacturer carry onto its own type 3.1 or 3.2 certificate the results of specific inspection on the primary or incoming material it uses, if it operates traceability procedures and can supply the matching inspection documents. So a component maker's certificate may carry mill results. Ask for the original mill certificate and match the heat number to it. Step 5 needs a public register, so that comes next.

How do you check the licence marking and status at goods receipt

A monogrammed tool is checked at goods receipt by finding the mark and licence number on the tool, searching that number on the public API Composite List, and reading the facility, scope and status on the record.

The API Composite List is API's public, searchable list of Monogram licensees, at compositelist.api.org. Only a licensee applies the API Monogram and its designated licence number, and a licence covers one facility. The register is updated in real time, and status changes such as suspensions or cancellations are posted when they are decided.

  1. Confirm that the purchase order line required a monogrammed tool.
  2. Find the mark and licence number on the tool or its nameplate and on the conformance document, and confirm that both show the same number.
  3. Search the number exactly as marked on the API Composite List at compositelist.api.org.
  4. Read the facility, the products or specification in scope, and the status. Match them to the purchase order line and to where the tool says it was made.
  5. Save the record to the receiving file, and repeat the check on every receipt, because the register is updated in real time.

There are three outcomes. If the record matches, continue with the remaining checks. If the number is not found, the status is not active, or the scope does not cover the order line, hold the tool and raise a non-conformance report. If the order required a mark and the tool has none, that is a non-conformance to the order, not a paperwork query.

API also keeps a fraud alerts page that lists certificates it did not issue, where a listing means only that API did not issue the certificate. Suspected fraud is reported through the Monogram and APIQR contact form. The full method for reading a licence number and every status has its own guide. The second independent source is on the tool itself, and the next check reads it.

How do you match the heat number on the certificate to the component

The heat number links a material certificate to the steel in the component, so the number on the certificate must match the number marked on the tool or in the supplier's traceability record.

  1. Read the heat or lot number on the certificate.
  2. Find the same number on the component, as a hard stamp or other marking, and check that it is legible.
  3. Check that the grade and specification on the certificate equal those on the order and the drawing.
  4. Check that each reported chemistry and mechanical value sits inside the limits the certificate itself prints for the grade.
  5. Where the finished tool is too small, or too finished, to carry a heat number, ask for the traceability record that links its serial or lot number to the heat, and match that record instead.

If the certificate came from a component maker rather than a mill, it may carry transferred mill results, which EN 10204 allows. Ask for the original mill certificate and match the heat number to that document as well.

Positive material identification (PMI) is a fast, non-destructive check of a metal's elemental composition and alloy grade, and the handheld XRF analyser is the most common method. It tests the alloy without relying on the supplier's paper. ASTM E1476 covers metals identification, grade verification and sorting. PMI identifies the grade but does not replace the certificate, and it cannot report carbon. Use it where the order requires it, or where a mismatch raises doubt.

Signs of an altered certificate include a layout that differs from the mill's known format, misaligned table rows, altered file properties and values that are implausible for the grade. When a certificate looks altered, verify it with the issuing mill or, for a type 3.2, the endorsing body. Use independent contact details, not those printed on the certificate. What the paper cannot show, the gauge can, and the next check uses one.

Need expert guidance on the right solution?

Talk to our engineers about your project requirements.

Book a Consultation

Which dimensional and visual checks belong at goods receipt

Dimensional and visual checks at goods receipt confirm that the tool in the crate is the tool on the drawing and that it arrived undamaged, using your own calibrated instruments rather than the supplier's report. Incoming inspection checks cover measured features, surface condition, quantity, transit damage, preservation and end protection.

Dimensional inspection starts with the critical features named on the drawing, such as thread forms, outside and inside diameters and seal surfaces. Use calibrated gauges and, where the feature needs it, a coordinate measuring machine (CMM) or a thread inspection gauge set. Record the identification of every instrument. Compare your readings with the supplier's dimensional report and with the drawing. A reading that agrees with the report confirms the report. A reading that disagrees is a finding.

The visual inspection covers:

  • marking legibility;
  • transit damage;
  • corrosion;
  • thread protectors and end protection fitted;
  • seals and sealing surfaces undamaged;
  • preservation intact;
  • quantity against the packing list.

ISO 2859-1 is a lot-by-lot acceptance sampling system by attributes, indexed by acceptance quality limit (AQL). It applies to components, raw materials and records, among other items, and it is intended for a continuing series of lots. Engineered-to-order tools tend to arrive in small lots, where a sampling table gives little. Many procedures measure the critical features of every unit and sample the rest. That is common practice, not a rule of any standard. Record the sample size you used and the reason for it. When a reading fails, the next step is a non-conformance report.

How do you raise a non-conformance when the paper and the tool disagree

A non-conformance report (NCR) records what was ordered, what was found, the evidence, and what happened to the goods, so that the supplier can correct it and the buyer can show that the tool was never used. A report holds seven items:

  1. A unique report number.
  2. The order, line, part number, serial or lot number and quantity.
  3. The requirement, quoted from the order, the drawing or the specification.
  4. The finding, with readings, photographs and the register record where a licence check failed.
  5. Where the goods are held, and the tag on them.
  6. Who decided, and what was decided.
  7. The request to the supplier.

ISO 9001 clause 8.7 requires nonconforming outputs to be identified and controlled to prevent unintended use or delivery, and it counts product received from an external provider as one that can be nonconforming. It also calls for records of the nonconformity, the actions taken, any concessions obtained and the authority that decided. The seven items above cover all four. Common disposition terms are accept, accept with concession, quarantine and return.

Quarantine means physical separation plus a hold tag, so that the tool cannot be issued by mistake.

The supplier notification asks for a supplier corrective action request (SCAR) answer, a corrected document where the error is in the paper, and replacement or rework where it is in the product. A corrective action is closed only when the supplier's response is checked against the tool or the document.

If a certificate looks forged rather than mistaken, do not return the tool or the document quietly. Keep the evidence, escalate to the QA lead, and report through the issuing body's route. With the evidence held and the supplier notified, the decision comes next.

When should you reject, hold or accept with a concession

The decision at goods receipt depends on what failed: a check against an outside source, a paper error that leaves the product intact, a measurement outside tolerance, or damage. The table shows common practice. Your procedure and your order terms govern, and the usual decision changes if the order says otherwise.

What the check foundUsual decisionWho decides
A check against an outside source contradicts the paper: a licence number not found on the register, a heat number on the tool that is absent from the certificate, or a certificate the mill has no record of issuing.Reject, or hold and escalate as a suspected forgery.QA lead
A paper error that leaves the product intact, such as a mistyped order reference, a missing signature or the wrong type letter, while every outside check agrees.Hold until a corrected document arrives.QA
A critical feature measured outside tolerance.Reject.QA
A non-critical feature outside tolerance.Accept with concession only if the design authority agrees and the concession is recorded. A concession is sometimes called a deviation permit.Engineering
Damage in transit.Accept, repair or reject by the type of damage and its effect on sealing and threads, with a claim against the carrier.QA with engineering

When every check passes, the tool is accepted and released, and the record names who authorised the release. That person is the release authority under ISO 9001 clause 8.6. Concessions and the authority that decided them are recorded under ISO 9001 clause 8.7.

The principle under every row is to verify against independent sources wherever one exists: the API Composite List for the licence, the heat number on the component for the material certificate, and your own purchase order for the certificate type. A document that only agrees with other documents from the same supplier has not been verified. Every decision, and the evidence behind it, then goes into the file.

What should the inspection record add to the supplier-qualification file

The supplier-qualification file should hold a receiving record for every shipment, the evidence behind each independent check, every non-conformance and its closure, and the re-verification of the supplier's management-system certificates. In practice that means six items:

  1. The receiving record: the order, the documents received, the checks run, the results, the inspector and the decision.
  2. The evidence for each independent check: the register record, the heat number match, and the readings with their instrument identifications.
  3. The date of the check beside each piece of evidence.
  4. Every non-conformance, with the supplier's response and the non-conformance closure.
  5. The supplier's management-system certificates, with certificate number, certification body, scope and certified locations, rechecked on the accreditation database at each file review.
  6. A running count of accepted, held and rejected receipts, so that a trend is visible.

IAF CertSearch shows status, standard and scheme, scope, certified locations, the certification body and the accreditation body, for accredited certificates only. A search needs the certified entity's name or the certificate number. ISO itself does not certify, and it directs readers to CertSearch or to the certification body.

Re-verify when a certificate or a status changes, when the supplier's plant or process changes, after a rejected shipment, and at each scheduled review of the supplier file. A supplier on the approved vendor list is not exempt. A certificate that is not found on the database may be unaccredited, or the search details may not match, so confirm it directly with the certification body named on it. That is where incoming inspection ends, and the next section marks where this guide stops.

Where does incoming inspection end and the rest of supplier approval begin

Incoming inspection answers whether this shipment matches the order and its documents, and says nothing about whether the supplier is approved, whether the tool was tested properly, or whether the tool has a record in the field. It covers one shipment at receipt. The table below draws the boundary and says what this guide does with each neighbouring question.

QuestionWhere it is settledWhat this guide does
Is the supplier approved, and is its quality system real?Supplier approval and the supplier auditCovers only the receiving side of certificate checks.
What must a material test report show?The material test report guideOne sentence in the document table; the rest is its own subject.
How do you read a licence number and decode statuses?The register guideCovers the one receiving step.
Was the tool tested properly before dispatch?The factory acceptance test (FAT)Not covered. The certificate of the test is checked here.
Has this tool type run in the field, and is there a field record?Field referencesNot covered.
Which management-system certificates does a manufacturer need?The ISO certificates guideCovers the receiving file only.
Do the export documents match the consignment?The export documentation packNot covered.

The certificate of a factory acceptance test is one of the documents checked at receipt, even though the test itself sits outside this guide. Each of the other topics has its own guide. With the boundary drawn, the remaining question is what a manufacturer sends for your check.

What does Maximus OIGA Private Limited send with a tool, so your receiving check has something to match

Maximus OIGA Private Limited manufactures SpectraMax downhole completion equipment, engineered to order at its plant at Plot 365, Savli GIDC Road, Alindra, Vadodara, Gujarat 391776, India.

Each shipment includes material test reports traceable to the heat, dimensional inspection reports, a pressure test certificate for each unit, and the applicable certificates of conformance. Every unit is pressure tested and dimensionally inspected before it leaves the plant. These are the documents a receiving team can match against the checks in this guide.

A plant audit by arrangement is open to customer QA and procurement teams at the Vadodara plant. The company also provides vendor registration documents on request, covering company, quality, product and plant documents. The first step is requesting the documents, and the first shipment is where the checks in this guide are run.

If your QA team is building a receiving procedure or qualifying a supplier, the document set from Maximus OIGA Private Limited gives it real documents to run these steps on.

Frequently asked questions

How to check mill test certificate?

Match the certificate to the order for grade, specification and certificate type. Match the heat number to the marking on the material. Check that each reported value sits inside the limits printed for the grade, and check who validated it. For a transferred result, ask for the original mill certificate. If doubt remains, verify with the issuing mill using independent contact details.

What is EN 10204 type 3.1 grade?

It is not a grade. EN 10204 type 3.1 is a kind of inspection certificate in which the manufacturer states that the products meet the order and gives test results, validated by an authorised inspection representative independent of the manufacturing department. Type 3.2 adds a second validator.

What is the difference between a mill test certificate and a material test certificate?

A mill test certificate and a material test certificate are, in practice, the same kind of document: a record of tests on a batch of material. Buyers use the two names interchangeably. What matters is the EN 10204 type printed on it and who validated it.

What is the difference between incoming inspection and receiving inspection?

Incoming inspection and receiving inspection name the same activity, and goods receipt inspection is a third name for it. Procedures and checklists use the three names interchangeably. Whatever the name, the job is to confirm that arrived goods match the order and the documents before release.

What should an incoming inspection checklist for a completion tool include?

An incoming inspection checklist for a completion tool should list the order and drawing revision, the document set, the certificate types and validators, the API Composite List record where the order requires a mark, the heat number match, the dimensional and visual checks, and the decision with the name of who made it. The seven-step sequence above gives the order.

Get to know Maximus OIGAExplore our products, capabilities, and certifications.Learn More

More Information

Related News & Insights

Insulating Packer Fluid: Selection for Thermal and Steam Injection Wells

Insulating Packer Fluid: Selection for Thermal and Steam Injection Wells

Insulating packer fluid sits in the annulus above the packer and cuts heat loss from tubing to casing by limiting conduction and convection. In steam injection and SAGD wells, choose it together with the packer, based on conductivity, high-temperature behavior, elastomer and casing compatibility, and removal at workover.

Read More

November 24, 2026

Frac Plug Setting Tools for Wireline Completions

Frac Plug Setting Tools for Wireline Completions

A frac plug setting tool has to match the plug on four points: stroke, setting force against the plug's shear value, the adapter kit and the power source. Baker-style size 10 and size 20 wireline tools are the common references, and the size follows the plug and the casing.

Read More

November 24, 2026

Shell and BP Supplier Qualification for Completion Equipment

Shell and BP Supplier Qualification for Completion Equipment

Shell and BP both pick suppliers through SAP Ariba sourcing events, after assessing financial position, technical capability and the ability to deliver safely. Qualification starts with the buyer's invitation, so equipment manufacturers should have their records ready before it arrives and register second.

Read More

November 24, 2026

HSE Documents an Oilfield Equipment Supplier Must Provide

HSE Documents an Oilfield Equipment Supplier Must Provide

This guide covers the HSE documents an oilfield supplier submits for vendor registration: the policy, manual, risk and legal registers, emergency plan, incident, training and audit records, and any ISO 45001 or 14001 certificate. It shows what each one must contain, and how operators check it against the sites and work it claims to cover.

Read More

November 20, 2026

Which API Specification Covers Which Tool, and How to Read a Licence Number

Which API Specification Covers Which Tool, and How to Read a Licence Number

A certificate on a letterhead isn’t proof. This guide maps common completion tools to the API specifications that cover them, explains how an API Monogram licence number is built, and shows how to check it on the API Composite List before a part reaches incoming inspection.

Read More

November 20, 2026

Petrobras Supplier Registration for Oilfield Equipment Manufacturers

Petrobras Supplier Registration for Oilfield Equipment Manufacturers

Which HSE documents an oilfield equipment supplier is asked for at vendor registration, what each one must contain and how operators check them. It covers the HSE policy, manual, registers, emergency plan, and incident and training records.

Read More

November 20, 2026

Sonangol Angola Vendor Registration for Completion Equipment Suppliers

Sonangol Angola Vendor Registration for Completion Equipment Suppliers

How completion-equipment suppliers register to sell in Angola. Registration on the ANPG portal comes first, because only registered suppliers can bid. Sonangol vendor registration comes second and covers Sonangol’s own companies.

Read More

November 20, 2026

NNPC Nigeria vendor registration for oilfield equipment suppliers

NNPC Nigeria vendor registration for oilfield equipment suppliers

How NNPC vendor registration on SAP Ariba and NipeX NJQS qualification work, and why the bidder is in practice a Nigerian-registered company. Written for Nigerian bidders and the overseas makers who supply them: who files what, how Nigerian content is scored, and how SpectraMax tools clear into Nigeria.

Read More

November 20, 2026

Markets We Supply: Lead Times, Export Documentation and Field References

Markets We Supply: Lead Times, Export Documentation and Field References

Maximus OIGA builds SpectraMax completion tools to order at its Vadodara plant. It ships to India, the Middle East, Southeast Asia and the US, with quality records and export papers included in every order.

Read More

November 20, 2026

The documentation pack an operator will ask you for

The documentation pack an operator will ask you for

What a downhole tool's documentation pack must contain — mill test reports, heat traceability, the ITP and certificate of conformity — and nine checks to run before you sign off.

Read More

October 20, 2026